Bells Pocket Road Stormwater Drainage Upgrade Cover 1
Bells Pocket Road Stormwater Drainage Upgrade Cover 2
Bells Pocket Road Stormwater Drainage Upgrade Cover 3

Bells Pocket Road Stormwater Drainage Upgrade


Project Scope

As part of the continuing upgrade of existing storm water facilities in the heart of Strathpine, this project included the following:

  • 528m of new stormwater pipework from 375mm diameter to 1,050mm diameter.
  • 80m of 1,500mm jacked pipe beneath Strathpine Rd across the intersection of Bells Pocket Rd and Gympie Rd.
  • 600m of pavement reinstatement.
  • Landscaping of all disturbed areas.

  • Of particular importance was the requirement to accommodate all existing vehicular and pedestrian traffic throughout the site, as well as the arrangement of works around the shopping precinct through which the pipework was running.


    As a result of these requirements a large portion of these works were undertaken after hours, with particular attention being paid to the temporary reinstatement of road after each nights work. Essentially, daily reinstatement of sections of road prior to 5.00am were required to allow businesses and road users to operate with minimal disruption.


    Another innovation adopted under this contract was the utilisation of precast manholes and pits, which expedited the construction process and further minimised disruption to local enterprises.


    Ongoing community liaison, by Doval, was also required in order to keep shop-owners abreast of the works.

    The project was completed on time, within budget and to the satisfaction of the Client.



    Key Staff

  • Brett Marais – Contracts Manager
  • Jesse Horton – Project Manager
  • Cobby Roles – Site Supervisor
  • Andrew Duncan – Site Supervisor

  • Achievements

  • The accommodation of both vehicular and pedestrian traffic throughout the duration of the contract.
  • The installation of deep stormwater lines in restricted conditions.
  • The completion and phasing of the works in such a manner to minimise disruption to local business owners.
  • Night works and the reinstatement of sections of road at the end of each shift.
    • Project:

      Bells Pocket Road Stormwater Drainage Upgrade

    • Location:

      Strathpine, Qld

    • Client:

      Moreton Bay Regional Council

    • Practical Completion:

      February 2012

    • Contract Period:

      16 Weeks

    • Contract Value:

      $1.4 million